Security Class |
Purpose Type |
Description |
Final Maturity |
Amount |
General Obligation |
Other |
Refunding |
06-01-2029 |
$2,750,000.00 |
General Obligation |
Public Safety |
new fire hall |
06-01-2029 |
$2,020,000.00 |
General Obligation |
Transportation |
2012 Street Improvements (P Ave. and sealcoating) |
06-01-2023 |
$450,000.00 |
General Obligation |
Transportation |
Street reconstruction of E. 10th St., 18th St., and N Ave. near fire hall |
06-01-2021 |
$360,000.00 |
General Obligation |
Utilities/Sewers |
6th St. storm sewer portion of project |
06-01-2031 |
$285,000.00 |
Revenue Bonds |
Utilities/Sewers |
2011 6th St. sewer project |
06-01-2031 |
$1,160,000.00 |
Revenue Bonds |
Other |
2009 Highway 71 Sidewalk and Street Lighting Project |
06-01-2020 |
$0.00 |
Total Debt as of 2015: |
$7,025,000.00 |