Hawarden Outstanding Obligations
Security Class Purpose Type Description Final Maturity Amount
General Obligation Transportation 16th Street Improvement Project 06-01-2025 $515,000.00
Revenue Bonds Utilities/Sewers Wastewater Treatment plant- bonds paid as requested by lender. Not all funds borrowed as of 6-30-20 06-01-2040 $2,425,554.00
Revenue Bonds Utilities/Sewers Electric Upgrade Project Phase II 06-01-2034 $2,320,000.00
Revenue Bonds Utilities/Sewers Ele Rev Bond- South Feeder/ Transmission line 06-01-2039 $2,190,000.00
Revenue Bonds Utilities/Sewers Electric Revenue Bond 06-01-2031 $2,105,000.00
Total Debt as of 2021: $9,555,554.00

Fun Facts: