| Security Class | Purpose Type | Description | Final Maturity | Amount |
|---|---|---|---|---|
| General Obligation | Utilities/Sewers | Water Treatment Plant | 06-01-2040 | $2,985,000.00 |
| General Obligation | Other | Street Projects | 06-01-2028 | $1,050,000.00 |
| General Obligation | Transportation | Street Construction Main St/1st St | 06-01-2027 | $190,000.00 |
| Revenue Bonds | Utilities/Sewers | Wastewater Treatment Plant Expansion | 06-01-2040 | $7,722,659.94 |
| Revenue Bonds | Utilities/Sewers | Water Treatment Plant | 06-01-2041 | $3,580,000.00 |
| Revenue Bonds | Utilities/Sewers | Electric Substation Project | 08-01-2028 | $965,000.00 |
| Revenue Bonds | Utilities/Sewers | New Electric Substation Project | 09-30-2032 | $835,000.00 |
| Revenue Bonds | Utilities/Sewers | Wastewater Expansion | 06-01-2025 | $60,000.00 |
| Total Debt as of 2024: | $17,387,659.94 | |||