| Security Class | Purpose Type | Description | Final Maturity | Amount |
|---|---|---|---|---|
| General Obligation | Transportation | 3rd Street N Bridge | 12-01-2042 | $343,901.00 |
| Revenue Bonds | Utilities/Sewers | Wastewater Treatment Plant Improvement Project | 02-13-2059 | $2,124,230.34 |
| Revenue Bonds | Utilities/Sewers | Wastewater Treatment Plant Mercury Cleanup Project | 02-13-2059 | $608,270.04 |
| Loans | Public Safety | Fire truck | 04-30-2030 | $71,942.44 |
| Total Debt as of 2024: | $3,148,343.82 | |||