Davenport Outstanding Obligations
Security Class Purpose Type Description Final Maturity Amount
General Obligation Other The $ 31,880,000 GO Bonds Series 2023 are issued for: sanitary sewers, streets, parks, vehicles, IT, Library, bridges, streetscapes, sidewalks. 06-01-2038 $31,880,000.00
General Obligation Other 2022A REFUNDING OF 2014A AND PROCEEDS OF THE BONDS ARE BEING USED TO PAY COSTS OF CARRYING OUT ESEENTIAL AND GENERAL CORPORATE PURPOSE PROJECTS. 06-01-2037 $29,420,000.00
General Obligation Other 2020A Improvements to sewers, streets, streetscape, sidewalks and paths, airport, housing proj., fire & police, and refunding 2012A & 2012D. 06-01-2035 $26,625,000.00
General Obligation Other 2016A GO streets, sewer, equipment, solid waste, facilities 06-01-2031 $25,205,000.00
General Obligation Other 2020B improvements to sanitary sewers, sewage treatment works, storm sewers, streets, streetscape, sidewalks & paths, airport, and miscellaneous 06-01-2036 $17,745,000.00
General Obligation Other 2018A GO CORPORATE AND REFUNDING BUNDS REFUNDING 2010A & 2010B 06-01-2026 $17,205,000.00
General Obligation Other 2019A Sanitary sewers, storm sewers, streets, airport, municipal housing projects, fire & police department parks and equipment 06-01-2034 $16,305,000.00
General Obligation Other 2017A 06-01-2032 $13,100,000.00
General Obligation Other 2015 GO issue sewers, streets, solid waste, buildings 06-01-2030 $8,180,000.00
General Obligation Other 2021A refunding 2013A 06-01-2032 $6,435,000.00
General Obligation Other 2018B TAXABLE GO CORPORATE AND REFUNDING BONDS. REFUNDING 2010C 06-01-2026 $5,060,000.00
General Obligation Other 2017C CROSSOVER REFUNDING OF 2010D 06-01-2025 $4,270,000.00
General Obligation Other 2017B REFUNDING OF 2009C COMMUNICATION BONDS 06-01-2029 $4,140,000.00
General Obligation Other 2016b advance refunding of 2008d and 2009b 06-01-2028 $1,935,000.00
Revenue Bonds Utilities/Sewers SRF #4 1930'S sanitary sewer riverfront interceptor 06-01-2040 $8,358,950.00
Revenue Bonds Utilities/Sewers srf loan 06-01-2041 $7,096,000.00
Revenue Bonds Utilities/Sewers UV disinfection project & gray water system addition project 06-01-2041 $6,359,026.00
Revenue Bonds Utilities/Sewers srf #3 plant optimization 06-01-2036 $4,357,022.00
Revenue Bonds Utilities/Sewers srf #2 06-01-2034 $3,301,000.00
Revenue Bonds Utilities/Sewers 28E WITH SOLID WASTE COMMISSION FOR SINGLE STREAM WASTE CARTS 07-01-2025 $600,387.00
Capital Leases/Lease to Purchase Parks/Recreation Yamaha-4889-4-000110 Golf cars lease. 02-28-2025 $142,016.00
Capital Leases/Lease to Purchase Parks/Recreation HARRIS GOLF CARTS 4889-000125 10-31-2027 $29,641.00
Capital Leases/Lease to Purchase Parks/Recreation M&M GOLF CARS 4889-4-000123 02-28-2028 $17,695.00
Capital Leases/Lease to Purchase Parks/Recreation Yamaha 4889-4-000108 Golf car lease. 02-28-2025 $16,882.00
Loans Transportation RAIL DEBT 06-30-2026 $93,237.00
Total Debt as of 2024: $237,876,856.00

Fun Facts: